1. If x men can do a work in y days, how many days will it take (x+4) men to do the same work?

  • A. y-4
  • B. y-4
  • C. y-4
  • D. y-4

Answer: Option C

Explanation:

Hints:

x men কাজটি করে y দিনে

1 man কাজটি করে xy দিনে

x + 4 men কাজটি করে xy/ (x + 4) দিনে