1. In a factory there are 3 machines to perform a job. The newest machine can do the job in 3 days, another machine can do it in 4 days, and the third machine can do it in 6 days. How many days will the factory take to do the job using all three machines together?

  • A. 1.333
  • B. 1.333
  • C. 1.333
  • D. 1.333

Answer: Option A

Explanation:

All three of the machines together can complete (1/3 + 1/4 + 1/6) = 3/4 part of the job in a day.

Those machines can complete 3/4 part of the job in 1 day.

So, the machines can complete the whole job in 1/(3/4) = 4/3 =  1.333 day. 