1. x can do a piece of work in 20 days and Y can do the 1/7th of the same work in 5 days. In how many days together they can complete the 11/14th of the total work?

  • A. 15 days
  • B. 15 days
  • C. 15 days
  • D. 15 days

Answer: Option C

Explanation:

y can do in 1 day = 1/(7x5) = 1/35
x & y can do in 1 day = 1/20 + 1/35 = 11/140
Now,
11/140 work is done in 1 day
So, 1 work is done in 140/11 day
So, 11/14 work is done in (140x11)/(11x14) = 10 days.