1. If Michael can shovel all the snow of a standard driveway in 12 minutes, and Emon can shovel all the snow of a standard driveway in 36 minutes, then working together, how many minutes would it take for them both to shovel all the snow of a standard driveway?

  • A. 5
  • B. 5
  • C. 5
  • D. 5

Answer: Option B

Explanation:

To find how long it would take for Michael and Emon to shovel the snow together, you can use the concept of their combined work rates.

Let M be Michael's work rate (driveways per minute) and E be Emon's work rate (driveways per minute).

Michael can shovel one driveway in 12 minutes, so his work rate is:

M = 1 driveway / 12 minutes = 1/12 driveways per minute

Emon can shovel one driveway in 36 minutes, so his work rate is:

E = 1 driveway / 36 minutes = 1/36 driveways per minute

When they work together, their combined work rate is the sum of their individual work rates:

Combined Work Rate = M + E = (1/12 + 1/36) driveways per minute

Now, find a common denominator to add the fractions:

Combined Work Rate = (3/36 + 1/36) driveways per minute = 4/36 driveways per minute

Simplify the fraction:

Combined Work Rate = 1/9 driveways per minute

Now that you know their combined work rate, you can calculate how long it would take for them to shovel one standard driveway together:

Time = 1 driveway / Combined Work Rate = 1 / (1/9) = 9 minutes

So, it would take Michael and Emon 9 minutes to shovel all the snow of a standard driveway together.