1. If ‘x’ men can do a work in 8 days and ‘x + 4’ men can do it in 6 days, what is the value of ‘x’?

  • A. 4
  • B. 4
  • C. 4
  • D. 4

Answer: Option D

Explanation:

Hints: x জন করে 8 দিনে

1 জন করে 8x দিনে

(x + 4) জন করে 6 দিনে

1 জন করে 6(x + 4) দিনে

এখন, 8x = 6x + 24

2x = 24

x = 12