1. A contractor employs 60 person for doing a job in 80 days. After 20 days it was found that only one-fifth of work was finished.How many more persons are to be employed to finish the job as per schedule?
- A. 20
- B. 20
- C. 20
- D. 20
Answer: Option A
Explanation: