1 . If 18 identical machines required 40 days to complete a job, how many fewer days would have been required to do the job if 6 additional machines of the same type had been used from the beginning?

  • A. 10
  • B. 13.33
  • C. 16
  • D. 26.66
View Answer Discuss in Forum Workspace Report