1 . If Masud can do a job in P days, while Minhaz can do the same job in Q days separately, how long will it take to finish the job if they work together?

  • A. (P+Q)/PQ days
  • B. PQ/(P+Q) days
  • C. (P+Q) days
  • D. (1/P + 1/Q) days