1 . If it takes 4 hours to dig a hole by 50 workers, how long should it take to dig the same hole by 30 workers?

  • A. 2 hours 24 minutes
  • B. 6 houres 12 minutes
  • C. 5 houres 12 minutes
  • D. 6 hours 40 minutes
View Answer Discuss in Forum Workspace Report