1 . If it takes 50 workers 4 hours to dig a hole, how long should it take 30 workers to dig the same hole?

  • A. 5 hours 12 minutes
  • B. 6 hours 40 minutes
  • C. 2 hours 24 minutes
  • D. 6 hours 12 minutes
View Answer Discuss in Forum Workspace Report