1 . A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in :
- A. 20 days
- B. 22.5 days
- C. 25 days
- D. 30 days
- E. 15 days
![]() |
![]() |
![]() |
![]() |
Bangladesh Bank - Assistant Director - 2011
More
2 . 20 workers can finish a task in 30 days. How many additional workers are needed to finish the same task in 25 days?
- A. 6
- B. 8
- C. 10
- D. 12
- E. None of these
![]() |
![]() |
![]() |
![]() |
3 . If 4 workers can do a job in 48 days, how long will it take 3 workers to finish the same job ?
- A. 76
- B. 72
- C. 70
- D. None of these
![]() |
![]() |
![]() |
![]() |
Bangladesh Bank - Assistant Director - 2001
More
4 . If 6 workers can complete 9 identical jobs in 3 days, how long (in days) will it take 4 workers to complete 10 such jobs?
- A. 5
- B. 4
- C. 6
- D. 3
- E. None of these
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Bangladesh Bank - Assistant Director - 2006
More
![]() |
![]() |
![]() |
![]() |
Bangladesh Bank - Assistant Director - 2009
More
![]() |
![]() |
![]() |
![]() |
Bangladesh Bank - Officer - 2001
More
8 . Tow workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked along, he would need 4.5 hours more to complete the job than they both working together. What time would they take to do the work together?
- A. 4 hours
- B. 5 hours
- C. 6 hours
- D. 7 hours
![]() |
![]() |
![]() |
![]() |
Bangladesh Bank - Assistant Director - 2014
More