1 . A can complete a piece of work in 12 days, A, B and C can complete the work in 6 days, Efficiency of B is 0.5 times the efficiency of In how many days C can complete the works= alone?
- A. 24 days
- B. 10 days
- C. 16 days
- D. 12 days
View Answer | Discuss in Forum | Workspace | Report |
Officer (General) |-Sonali | Janata | Bangladesh Krishi_Bangladesh Development bank ২৪.০৫.২০১৯
More